During 23–30 October 2026, the Bo Song Dinh project continued fabricating tank cover reinforcement for the wastewater treatment plant with a capacity of 120 m³/day. Coordination with electricity and water utilities to install household meters has reached 99%, according to the report.

During 23–30 October 2026, the Bo Song Dinh project continued fabricating tank cover reinforcement for the wastewater treatment plant with a capacity of 120 m³/day. Coordination with electricity and water utilities to install household meters has reached 99%, according to the report.
Contacting testing providers to assess the existing concrete road pavement for design purposes has reached 20%. This figure reflects progress in contacting providers, not completion of pavement testing.
The plan for 30 October–6 November 2026 includes preparing formwork, installing wastewater tank cover reinforcement and surveying earth material sources included in the draft list being prepared for auction.