Project progress: Bo Song Dinh New Urban Area
Blinding concrete is complete for the wastewater treatment plant with a capacity of 120 m³ per day. Phase 2 construction volume: 70%; survey of fill material sources: 50%; coordination on the communications system: 90%.

Blinding concrete is complete for the wastewater treatment plant with a capacity of 120 m³ per day.
Phase 2 construction volume: 70%; survey of fill material sources: 50%; coordination on the communications system: 90%.