Project Progress
Project progress: Kepler Land HH-02
Main construction items are reported as 100% complete. Defect rectification on floors 33–37 by multiple contractors is at 99%. 474/620 apartments have been handed over (approximately 76.5%): Tower C 202/279, Tower D 272/341.