Project progress: Armed Forces Housing, Xuan Phuong – OCT1, OCT3

Both towers have completed the listed ground anchor drilling layers. Pile caps and foundation tie beams are at 80% for both towers. Basement B3 slabs are at 50% for OCT1 and 65% for OCT3. Basement B2 slabs are at 50% for OCT1 and 35% for OCT3.

Project progress: Armed Forces Housing, Xuan Phuong – OCT1, OCT3

Both towers have completed the listed ground anchor drilling layers.

Pile caps and foundation tie beams are at 80% for both towers.

Basement B3 slabs are at 50% for OCT1 and 65% for OCT3.

Basement B2 slabs are at 50% for OCT1 and 35% for OCT3.