Project progress: Armed Forces Housing, Xuan Phuong – OCT1, OCT3
Pile caps and foundation tie beams are complete at OCT1 and OCT3. Basement B3 slabs have reached 100% at OCT1 and 80% at OCT3; B2 slabs are at 50% and 65%, respectively.

The report for 9–16 October 2026 records completion of all listed ground anchor layers, pile caps and foundation tie beams at both OCT1 and OCT3.
At OCT1, cumulative progress on the B3 slab is 100%; the B2, B1 and level 1 slabs are each at 50%. At OCT3, the B3 slab is at 80%, B2 at 65%, B1 at 45% and level 1 at 20%.
Next steps: OCT1 will continue B3 columns and walls, water tank walls and the B2 slab. OCT3 will continue the B3, B2, B1 and level 1 slabs, together with columns and walls.