Project Progress31/10/2026

Project progress: Housing for People’s Public Security Personnel, Phu Thuong – X1

The report for 23–30 October 2026 records completion of all 314 bored piles, 18 tank piles and 89 diaphragm wall panels at X1 Phu Thuong. Excavation and diaphragm wall chipping for the capping beam are complete over 462/462 metres; tube flushing and ultrasonic testing are complete for 23/23 wall panels.

Project progress: Housing for People’s Public Security Personnel, Phu Thuong – X1

The report for 23–30 October 2026 records completion of all 314 bored piles, 18 tank piles and 89 diaphragm wall panels at X1 Phu Thuong. Excavation and diaphragm wall chipping for the capping beam are complete over 462/462 metres; tube flushing and ultrasonic testing are complete for 23/23 wall panels.

Figures as of 29 October show capping beam reinforcement at 93.07%, formwork at 91.99% and concreting at 91.12%. Excavation and soil removal have reached 40,830/147,929 m³ (27.60%); first-layer anchors have reached 151/254. All three Type A reference points and all three groundwater monitoring wells are complete.

The following week’s plan focuses on completing the capping beam, continuing excavation and soil removal, installing first-layer anchors, and monitoring diaphragm wall movement and groundwater levels.