Project Progress17/10/2026

Project progress: Armed Forces Housing, Phu Thuong – X1

All 314 bored piles, 18 tank piles and 89 diaphragm wall panels are complete. Capping beam concreting is at 64.07%; excavation and soil removal are at 15.67%.

Project progress: Armed Forces Housing, Phu Thuong – X1

The report for 9–16 October 2026 records completion of all 314 bored piles, 18 water and treatment tank piles, and 89 diaphragm wall panels at X1 Phu Thuong.

Excavation for the capping beam is at 96.32%; diaphragm wall chipping is at 94.15%. Capping beam reinforcement is at 82.25%, formwork at 75.76% and concreting at 64.07%. Excavation and soil removal are at 15.67%; first-layer anchors are at 16/254 (6.3%).

The next work plan focuses on completing the reported capping beam works, continuing excavation and soil removal, installing first-layer anchors and inspecting the diaphragm walls.