Project progress: Housing for People’s Public Security Personnel, Xuan Phuong – OCT1, OCT3
Updated:
- The report for 23–30 October 2026 records completion of the B3 and B2 slabs at OCT1; the B1 and level 1 slabs are each at 50%. At OCT3, the B3 slab is complete, B2 and B1 are each at 85%, and level 1 is at 40%. These are reported cumulative quantities.
- Both towers have completed all listed ground anchor layers, pile caps and foundation tie beams. Tower crane erection is complete: 1/1 at OCT1 and 3/3 at OCT3.
- The following week’s plan is to continue B3 columns and walls, water tank walls and the B1 slab at OCT1. OCT3 will continue basement slabs, the level 1 slab, columns, walls and stairs.