Project progress: Armed Forces Housing, Xuan Phuong – OCT1, OCT3
- Both towers have completed the listed ground anchor drilling layers.
- Pile caps and foundation tie beams are at 80% for both towers.
- Basement B3 slabs are at 50% for OCT1 and 65% for OCT3.
- Basement B2 slabs are at 50% for OCT1 and 35% for OCT3.