Project progress: Armed Forces Housing, Xuan Phuong – OCT1, OCT3
Updated:
- The report for 9–16 October 2026 records completion of all listed ground anchor layers, pile caps and foundation tie beams at both OCT1 and OCT3.
- At OCT1, cumulative progress on the B3 slab is 100%; the B2, B1 and level 1 slabs are each at 50%. At OCT3, the B3 slab is at 80%, B2 at 65%, B1 at 45% and level 1 at 20%.
- Next steps: OCT1 will continue B3 columns and walls, water tank walls and the B2 slab. OCT3 will continue the B3, B2, B1 and level 1 slabs, together with columns and walls.