Project progress: Housing for People’s Public Security Personnel, Xuan Phuong – OCT1, OCT3

Project progress: Housing for People’s Public Security Personnel, Xuan Phuong – OCT1, OCT3

Updated:

  • The report for 23–30 October 2026 records completion of the B3 and B2 slabs at OCT1; the B1 and level 1 slabs are each at 50%. At OCT3, the B3 slab is complete, B2 and B1 are each at 85%, and level 1 is at 40%. These are reported cumulative quantities.
  • Both towers have completed all listed ground anchor layers, pile caps and foundation tie beams. Tower crane erection is complete: 1/1 at OCT1 and 3/3 at OCT3.
  • The following week’s plan is to continue B3 columns and walls, water tank walls and the B1 slab at OCT1. OCT3 will continue basement slabs, the level 1 slab, columns, walls and stairs.
Read update →
Project progress: Housing for People’s Public Security Personnel, Phu Thuong – X1

Project progress: Housing for People’s Public Security Personnel, Phu Thuong – X1

Updated:

  • The report for 23–30 October 2026 records completion of all 314 bored piles, 18 tank piles and 89 diaphragm wall panels at X1 Phu Thuong. Excavation and diaphragm wall chipping for the capping beam are complete over 462/462 metres; tube flushing and ultrasonic testing are complete for 23/23 wall panels.
  • Figures as of 29 October show capping beam reinforcement at 93.07%, formwork at 91.99% and concreting at 91.12%. Excavation and soil removal have reached 40,830/147,929 m³ (27.60%); first-layer anchors have reached 151/254. All three Type A reference points and all three groundwater monitoring wells are complete.
  • The following week’s plan focuses on completing the capping beam, continuing excavation and soil removal, installing first-layer anchors, and monitoring diaphragm wall movement and groundwater levels.
Read update →
Project progress: Song Dinh Riverfront New Urban Area

Project progress: Song Dinh Riverfront New Urban Area

Updated:

  • During 23–30 October 2026, the Bo Song Dinh project continued fabricating tank cover reinforcement for the wastewater treatment plant with a capacity of 120 m³/day. Coordination with electricity and water utilities to install household meters has reached 99%, according to the report.
  • Contacting testing providers to assess the existing concrete road pavement for design purposes has reached 20%. This figure reflects progress in contacting providers, not completion of pavement testing.
  • The plan for 30 October–6 November 2026 includes preparing formwork, installing wastewater tank cover reinforcement and surveying earth material sources included in the draft list being prepared for auction.
Read update →
Project progress: Kepler Land HH-02

Project progress: Kepler Land HH-02

Updated:

  • The report for 23–30 October 2026 records 250/279 apartments handed over in Tower C and 315/341 in Tower D at Kepler Land HH-02, for a total of 565/620. This is an increase of nine apartments from the previous report (556/620).
  • The project continues rectifying outstanding items alongside apartment handovers. The following week’s plan is to continue completing these works and handing over the remaining apartments in both towers. These figures cover HH-02 only and do not represent the entire HH01–HH02 complex.